The Government of India has undertaken the ambitious project of plying cargo ships from Haldia to Prayagraj on the river Ganga, also known as National Waterways-1 (NW-1). The justification for promoting waterways on such a massive scale as stated in National Waterways Bill, 2015 when introduced is as follows:
“…inland water transport is
recognised as fuel efficient, cost effective and environment friendly mode of transport, especially for bulk goods, hazardous goods and over dimensional cargos. It also reduces time, cost of transportation of goods and cargos, as well as congestion and accidents on highways.”
River Ganga near Farakka (Photo: Sarah Jamerson/Flickr)
As per the Government of India’s Press Release dated 21 July 2016, the cost of transportation of goods by rail was estimated at about Rs. 1.36 per ton kilometre, by waterways at Rs. 1.06 per ton kilometres and by road at Rs. 2.50 per ton kilometre. At first glance, the waterway appears to be far more economical.
Estimating Direct Costs
However, the rail and road routes more or less follow a straightened line. In contrast, rivers like Ganga in plains do not flow in a straight line. The Ganga meanders and that is why the actual distance of the Ganga River from Prayagraj to Haldia comes to about 1600 kilometres as compared to 955 km via railway and 884 km via road.
Now this means that even though the cost per ton kilometre of transportation via waterway is cheaper, in order to transport goods from Prayagraj to Haldia, ships will have to cover an extra 665 km and 736 km than rail and road respectively. The table demonstrates that the cost of transportation by National Waterways-1 is certainly not cheaper than rail. Also, waterways are the slowest mode of transport, which will further increase the opportunity cost.
Therefore, looking at the economics of waterway only from the standpoint of per ton kilometres cost of transportation is incorrect. At the end of the day what matters is whether the cost of transport from Prayagraj to Haldia is cheaper via waterway or not? In fact, the actual cost of transport on NW1 may be higher because of large investments that need to made by the Inland Waterways Authority and other agencies in making multi modal transport terminals like at Varanasi, Badh and Haldia. For full fledged commercially feasible waterways, there will be requirement of other infrastructure as well to support the ships such as riverside jetties, ports, handling sites, godowns, barge repairing & service stations, parking, fueling stations etc.
As per IWAI, to facilitate movement of 1000 to 2000 DWT cargo vessels, the navigational channel should have at least 45-meter width and 3-meter depth. Cost will further increase as not only there will be investment in capital dredging, but periodic maintenance dredging will be also required on river bed.
Let’s not forget that the goods transported via waterways will still require railways or road transportation for door-to-door delivery from ports, the cost of which and the associated infrastructure requirements are not even factored in yet. National Waterways-1 and other waterways cannot be commercially functional in isolation unless it is linked with other waterways and other transportation modes for which projects like Sagarmala are proposed which is bound to create a mass environmental disaster by altering the river ecosystems in the country. As per the Integrated National Transportation Waterway Grid Study undertaken by IWAI in 2014, an indicative investment of Rs. 22763 crore (public) and Rs. 65,599 (private) is required to develop infrastructure such as fairway, terminals, ports, road and rail connectivity. In 2016, 106 additional rivers were declared as new National Waterways (NW-6-NW111) without even considering whether they are economically feasible and ecologically sustainable.
If the interest and depreciation cost of these investments, increased length and dredging are added onto the waterway than the economics of the waterway would become even more adverse and the cost of transportation per ton kilometres may exceed much more than our existing transportation like road and rail. This fact is substantiated in the 2014 study Integrated National Waterways Transportation Grid Study (Stage 1 of Phase II) by RITES, the relevant excerpt of which is reproduced here:
IWT is the cost effective mode of transport and offers least vehicle operating cost/ charges as compared to Rail and Road. The level of advantage offered by IWT is much higher when compared with road than that of rail, but corresponding advantage goes adverse when terminal costs involved in the case of IWT also forms cost of comparison
Adverse Impacts on Environment
The environmental impacts of the waterway, particularly the ‘Gangetic Dolphin’, the national aquatic animal cannot be ignored. It is a blind animal and navigates by sound using echolocation. It also catches its prey by using sound waves generated from the prey movements. Movement of large ships will create a huge sound impact in the water channel and will make it particularly difficult for the dolphins to survive in the river.
The impacts are not just limited to disturbance created due to noise. Activities like dredging which are bound to take place on a massive scale will cause tremendous destruction to other aquatic flora and fauna. Riverbed is the place where large number of aquatic animals such as fish and turtles lay their eggs. Therefore continuous dredging of shallow area will disturb the aquatic habitat of these animals. Also by dredging the river to convert it into a mere water channel of 45 meters wide and 3 meters deep will remove shallow areas which are necessary for the egg laying and other activities of aquatic animals.
The National Waterways-1 also overlaps with the high biodiversity value zones of River Ganga assessed by the Wildlife Institute of India in its 2018 report Ganga River: State of Biodiversity at a glance. A Turtle Sanctuary in Varanasi is also being denotified to make way for the National Waterways-1. It is particularly interesting to know that the National Waterways-97, also termed as Sunderban waterways includes 14 different rivers in the highly fragile ecosystem of Sunderban which is also an UNESCO World Heritage Site, a habitat of precious wildlife, the future of which is already endangered due to salt water intrusion, loss of islands due to reduced sediment delivery because of dams upstream, climate change and several other anthropogenic pressures.
Map showing biodiversity rich stretches of River Gaga. Source: Ganga River: State of Biodiversity at a glance, Namami Gange, Wildlife Institute of India, May 2018
The National Waterways in the present scenario appears to be clearly unfeasible and will not benefit the national economy. It will in fact significantly harm the economy. The associated environmental and social damage due to alteration of the river and development of infrastructures will also add up to the economic disadvantage, the monetary cost of which is yet to be assessed. All this at a cost of a debt of US$ 375 million (approx. Rs. 2683 Crores) from the World Bank.
Suggested Readings:
- Should we relook at the 111 National Waterways? Shripad Dharmadhikari and Jinda Sandbhor, Ganga Today, July 2018. Link
- National Inland Waterways in India-A Strategic Status Report, Shripad Dharmadhikary & Jinda Sandbhor, Manthan Adhyayan Kendra and SRUTI, March 2017. Link
- A River Dolphin’s Ear-View Of India’s Waterways Development Plans, Nachiket Kelkar, Sanctuary Asia, February 2017. Link
- Turning Blind Eyes: Do we care for river dolphins or their habitat?, Nachiket Kelkar, SANDRP, October 2016. Link
- Impacts of Ganga Waterways Plan on its ecology and the people, Debadityo Sinha, SANDRP, August 2016. Link
- In the Pits: the Ganga River, dredged to death, Nachiket Kelkar, SANDRP, June 2016. Link
- Digging Our Rivers’ Graves? Nachiket Kelkar, ,SANDRP, February 2016, Link
- Four Boats at a River Crossing along Ganga, Nachiket Kelkar, SANDRP, December 2015.Link
- Losing our rivers to grand plans, Shripad Dharmadhikary, India Together, September 2015. Link
- Integrated National Waterways Transportation Grid Study (Stage 1 of Phase II), Final Report, RITES, Gurgaon. Published by Inland Waterways Authority of
India, New Delhi, 2014. Link - National Mission for Clean Ganga’s Biodiversity Programme Reports. Link
- Presentations of IWAI on Waterways. Link
—
*Environmentalist and Senior Resident Fellow at New Delhi based think tank Vidhi Centre for Legal Policy, also associated with Vindhyan Ecology and Natural History Foundation, Mirzapur (Uttar Pradesh) and Ganga Today, Lakshmoli (Uttarakhand). Contact: Twitter @debadityo, debadityo@vindhyabachao.org
*This article was first published in https://sandrp.in/