families | SabrangIndia News Related to Human Rights Thu, 26 Sep 2019 13:58:51 +0000 en-US hourly 1 https://wordpress.org/?v=6.2.2 https://sabrangindia.in/wp-content/uploads/2023/06/Favicon_0.png families | SabrangIndia 32 32 Supreme Court hears Pleas of Project Affected Families: Sardar Sarovar https://sabrangindia.in/supreme-court-hears-pleas-project-affected-families-sardar-sarovar/ Thu, 26 Sep 2019 13:58:51 +0000 http://localhost/sabrangv4/2019/09/26/supreme-court-hears-pleas-project-affected-families-sardar-sarovar/ After passing an interim order directing that the four chief ministers meet to resolve the acute crisis caused by imminent submergence, the Supreme Court today heard the Writ Petition under Article 32 of the Constitution, filed by the Project Affected Families (PAFs) in Madhya Pradesh. The Petitioners have averred that the filling of the Sardar […]

The post Supreme Court hears Pleas of Project Affected Families: Sardar Sarovar appeared first on SabrangIndia.

]]>
After passing an interim order directing that the four chief ministers meet to resolve the acute crisis caused by imminent submergence, the Supreme Court today heard the Writ Petition under Article 32 of the Constitution, filed by the Project Affected Families (PAFs) in Madhya Pradesh. The Petitioners have averred that the filling of the Sardar Sarovar Reservoir was illegal and in violation of law, State policies and the judgements of the Court.

Image result for supreme court of india
Image Courtesy: livemint.com

The States of Gujarat and Maharashtra, in addition to the State of Madhya Pradesh, and the inter-State body of Narmada Control Authority, were impleaded through an interim order passed by Justice Ramana and Justice Ajay Rastogi on the September 18, 2019.
 
The affidavits in reply filed by the Union of India and the Narmada Control Authority have rejected, among others, the plea for reducing the water level in the Sardar Sarovar to 122m by keeping the gates open. The affidavits have also claimed that the Narmada Control Authority and its various subgroups, for Resettlement and Rehabilitation (R&R) as well as environment, have already granted all the requisite permissions for filling of the reservoir to FRL in 2017 itself.
 
The State of Gujarat has also contended that the Supreme Court’s order of February, 8, 2017, had directed all the PAFs to vacate the villages by  July 31, 2017 and that this should have been complied with. 
 
The Petitioners, on the other hand, submitted that thousands of families, as indicated in the letter by the Chief Secretary of Madhya Pradesh dated May 27, 2019, have been residing in 76 villages, and their R&R remains pending.  The said letter stated that about 3000 applications by the claimants are pending, for the land entitlement or 60 lakh rupees package, granted by the Supreme Court itself in its 2017 order. It was also accepted that a number of tasks related to R&R remain pending and the civic amenities as per NWDTA & State policy, such as drinking water, roads, drainage and others, were not in place. 
 
Today, a Bench comprising of Justice N.V. Ramana, Justice Sanjiv Khanna and Justice Krishna Murari heard the Senior Counsel for the Petitioners, Sanjay Parikhji, who pointed out the gravity of submergence affecting human life and livelihood and requested that on account of the fact that R&R has not been completed, the rise in water levels was not in accordance with law and therefore, it should be brought down so that human sufferings are lessened.
 
Senior counsel for the M.P. government, Kapil Sibal sought time to file an affidavit pointing out the status of R&R. He also asserted that the impact of submergence is much more severe than what has been presented. Tushar Mehta, Solicitor General, submitted on behalf of the Union and NCA that water level in reservoir has been raised as per the procedure in the award. 
 
The Court, after hearing all the parties, directed the State of Madhya Pradesh to file an affidavit by September 30 and fixed the matter for hearing on 1st October. The Court also drew attention of the Solicitor General to the provision in NWDTA regarding a Review Committee meeting suggested in the interim order and observed that a decision should be taken in the meanwhile. It may be pointed out that the Review Committee comprises of the Chief Ministers of the 4 States- Madhya Pradesh, Maharashtra, Gujarat and Rajasthan as members, chaired by the Minister for Water Resources of the Union of India. 
 
The present crisis and controversy has arisen because the State of Gujarat wanted to increase the water level to 138.68 m in spite of State of Madhya Pradesh resisting it on the ground that the pending rehabilitation, submergence cannot be done and the R&R of thousands of families still pending. Because of the rise in water level in Sardar Sarovar, 176 villages have been submerged severely impacting their life and livelihood- islands/tapoos have been created, roads have been submerged and communication is severely affected.  
 
Related Articles:
1.      Four CMs must Meet, resolve contentious rehabilitation issue, on Narmada: SC
2.       Narmada valley: SC notice to Gujarat, MP, M’rashtra on submergence sans rehabilitation
 
 

The post Supreme Court hears Pleas of Project Affected Families: Sardar Sarovar appeared first on SabrangIndia.

]]>
Jharkhand riverine terminal: 485 families ‘displaced’: Lose land, livelihood in Sahibgunj https://sabrangindia.in/jharkhand-riverine-terminal-485-families-displaced-lose-land-livelihood-sahibgunj/ Thu, 12 Sep 2019 05:09:38 +0000 http://localhost/sabrangv4/2019/09/12/jharkhand-riverine-terminal-485-families-displaced-lose-land-livelihood-sahibgunj/ Even as Prime Minister Narendra Modi proposes to inaugurate on Thursday India’s second riverine Multi-Modal terminal (MMT) at Sahibganj in Jharkhand, built at a cost of Rs 290 crore reportedly in a record time of about two years, several civil rights organizations* have said that the government has failed to address the high-profile terminal’s social […]

The post Jharkhand riverine terminal: 485 families ‘displaced’: Lose land, livelihood in Sahibgunj appeared first on SabrangIndia.

]]>
Even as Prime Minister Narendra Modi proposes to inaugurate on Thursday India’s second riverine Multi-Modal terminal (MMT) at Sahibganj in Jharkhand, built at a cost of Rs 290 crore reportedly in a record time of about two years, several civil rights organizations* have said that the government has failed to address the high-profile terminal’s social and environmental concerns.

While the Government of India claims that the terminal would open up industries of Jharkhand and Bihar to the global market and provide Indo-Nepal cargo connectivity through waterways route, and some of the commodities with will be transported would include coal, stone chips, fertilizers, cement and sugar, a statement by the civil rights organizations says that the people of Sahibganj have “lost their land and are on the edge of losing their livelihood.”

The second Jal Marg Vikas Project – the first one being the MMT at Varanasi, inaugurated by the Prime Minister in November last year – has left people of the area “distressed with the process of resettlement and compensation, discrepancies in the resettlement surveys”, the statement says.

Text:

We have learnt that the Prime Minister is going to dedicate tomorrow to the nation the second riverine Multi-modal terminal at Sahibganj in Jharkhand, even when many of the concerns regarding the social and environmental impact remain to be addressed. It is claimed that the terminal has been built in record time, and certainly one of the reason is the brushing aside or neglect of these serious issue. We are deeply concerned by the neglect of these concerns by the authorities.

This terminal is second of the three Multi-modal terminals constructed under the Jal Marg Vikas Project or National Waterway-1, which is a World Bank funded project on river Ganga. These Multi-modal terminals are meant to provide link between the three modes of transport – railways, roadways and waterways. The Sahibgunj Multi-modal terminal is being pushed to open up industries of Jharkhand and Bihar to the global market and provide Indo-Nepal cargo connectivity through waterways route.

The Sahibganj terminal is built on the land (estimated requirement) of 195 acres of which 183.13 acres of main terminal and 9.24 acres for road connectivity has been fully acquired under Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement (LARR) Act, 2013. The terminal is to be developed in two phases – this inauguration is for the first phase of the terminal. Around 485 families have been identified as project affected families; resettlement of many families is yet to be done.

The people of Sahibganj have lost their land and are on the edge of losing their livelihood due to the Multi-modal terminal. They are distressed with the process of resettlement and compensation, discrepancies in the resettlement surveys, and have contacted the authorities to address their issues but to no avail. Further, a freight village (industrial cum logistic park and integrated vessel repair and maintenance complex) is also proposed on 335 acres of land in contiguity with the terminal which means more displacement is being lined up.
 

The Multi-modal terminal is likely to have several serious adverse impacts on the environment. Firstly, the terminal will aid the transportation of domestic coal from local mines in Rajmahal areas to various thermal power plants located on the National Waterway-1 on Ganga. Other than coal, stone chips, fertilisers, and cement are other commodities which are expected to be transported through the terminal.
 

Serious adverse impacts on the environment are likely due to loading/unloading and storage of  coal, stone chips, fertilisers, and cement

 

Serious adverse impacts on the environment are likely due to loading/unloading and storage of these commodities. The dredging to keep the passage to the terminal navigable, the noise and disturbance due to movement of ship, leakage of oil and lubricants, all are likely to have a serious impact on the river flora and fauna, especially the fish. Livelihoods of the fishing communities are also likely to be affected.

Given the scale of the terminal and seriousness of the adverse impacts on the environment, one would expect a strong environmental governance regime. Instead of strengthening and implementing the existing laws which require the terminal to take prior environmental clearance, Ministry of Shipping facilitated these Multi-modal terminals to circumvent the provisions of the Environment Impact Assessment Notification, 2006 and getting these terminals exempted from the need to obtain an Environmental Clearance.

We, the undersigned, who have been working on the issues related to social, environmental and economic aspects of the inland waterways programs, express serious concern at these lapses and demand the following:
 

  1. To expedite the resettlement process with participation of the people of Sahebganj and as per the 2013 LARR Act.
  2. No more land acquisition, as is proposed for a private concern, untill and unless consent of 80% affected people are taken as per the LARR Act 2013. 
  3. Before any further construction takes place nodal ministries must ensure that the MMT at Sahibgunj applies for and gets the legally mandatory environmental clearance, and a proper environment impact assessment for the Multi-modal terminal and the Freight village in Sahibganj is carried out. 
  4. A large number of people would be loosing the livelihood due to construction of this terminal and hence alternate livelihood for the small boat owners engaged in local trading and fishing be developed. 

People of Jharkhand have bore the burnt of development and large scale resources have been acquired often ignoring the social and environmental concerns. We urge that Prime Minister of India do not condone the environmental violations and not inaugurate the Terminal, until all the concerns are addressed.

*The statement issued by: National Alliance for People’s Movements, Manthan Adhyayan Kendra, Bhumi Bachao Sangharsh Samiti, Ekal Nari Sashakti Sangathan, Adivasi Adhikar Manch, Karnpura Bachao Sangharsh Samiti, Adivasi Haq Bhumi Suraksha Morcha, JOSH, Gram Ganrajya Prakhand Samiti, Hadma Kisan Jan Sangathan, Omon Mahila Sangathan

Courtesy: Counter View

The post Jharkhand riverine terminal: 485 families ‘displaced’: Lose land, livelihood in Sahibgunj appeared first on SabrangIndia.

]]>